As with many operating medical facilities, bed space is a precious commodity.  
This facility being no exception, our team came up with the revolutionary 
concept of dividing the building in half and renovating one side from the 
bottom to the top, activating that side and then renovating the other side from 
the top to the bottom.  Obviously this required a number of late night switch -over’s
and shut downs to minimize interruptions but allowed the hospital to 
maintain services to some patients while achieving the much needed 
restoration.  
 
One obstacle we had to overcome was the need to keep the Dialysis Unit in 
operation at all times.  All restoration for this area had to be completed in one 
12-hour period on one weekend.  We overcame this challenge by 
coordinating all activities with other trades so that we could maximize our 
efficiency and minimize our impact on the overall project to complete the 
necessary restoration.